{"type":"video","version":"1.0","html":"<iframe src=\"https://www.loom.com/embed/8dea87f435a14ab6a27b494178019268\" frameborder=\"0\" width=\"962\" height=\"721\" webkitallowfullscreen mozallowfullscreen allowfullscreen></iframe>","height":721,"width":962,"provider_name":"Loom","provider_url":"https://www.loom.com","thumbnail_height":721,"thumbnail_width":962,"thumbnail_url":"https://cdn.loom.com/sessions/thumbnails/8dea87f435a14ab6a27b494178019268-00001.jpg","duration":157,"title":"SAT official #8_S3_Q3","description":"p:  The formula below is often used by project managers to compute E, the estimated time to complete a job, where O is the shortest completion time, P is the longest completion time, and M is the most likely completion time. E = O + 4M + p / 6 Which of the following correctly gives P in terms of E, O, and M ? \na:  P= 6E − O − 4M ;\n P= −6E + O + 4M ;\n P = O +4M + E /6 ;\n P = O + 4M - E /6 ;"}